CIRCULAR LINK HIGHWAY FROM MAIN ROADS OF (ERBIL -MOSUL ) UP TO (ERBIL - SALAHDIN ) IN ERBIL

  • This project is 15.661 km length circular link highway main road ( Erbil –Mosul ) to ( Erbil – Shaqlawa )and additional 5 km road from 100m main street to ifraz road road, circular link project is highway(2x3), each side minimum (15.25 m )width , in addition to main roads the project is including overall (9) side roads. Moreover, nominated project is including big interchanges structures include 11 bridge, one pedestrian bridge and 5 underpass. For provide traffic continuity in location of intersecting main Erbil entrance road with circular highway

  • Hemn group commenced the work in …15/3/2103…officially handed over to the client in …15/12/2016 Within these period our company implemented all the activities , earthwork by cutting (2000000 m3 ), filling( 2500000 m3) and applying subgrade layer ( 800000 m3)… concreting the structures by (60000m3 ) ,concrete curb 140000 ml, executing the drainage system by (59000 M.L ) different size of pipes line connecting those by ( 1200) concrete manholes , then laying pavements through sub base ( 791,682 m3), plant base course ( 961,528 m2 ) and finalizing with asphalt both binder and wearing course by ( 1,879,100 m2) beside the other items of highway construction such as guard rail ,lighting ,road marking, traffic sign …etc.